Gorakhpur Link Expressway
Gorakhpur Link Expressway | |
---|---|
Route information | |
Maintained by Uttar Pradesh Expressways Industrial Development Authority (UPEIDA) | |
Length | 91.352 km (56.764 mi) |
Existed | December 2023[1]–present |
Major junctions | |
North end | Jaitpur village, Gorakhpur district |
South end | Salarpur village, Azamgarh district |
Location | |
Country | India |
State | Uttar Pradesh |
Highway system | |
State Highways in Uttar Pradesh |
Gorakhpur Link Expressway is an under-construction 91 km (57 mi) long, 4-lane wide (expandable to 6) expressway in the Indian state of Uttar Pradesh. It will connect Jaitpur village on NH-27 in Gorakhpur district with Salarpur village on Purvanchal Expressway in Azamgarh district.[2] Salarpur village is situated near Kalwari Bagh interchange (NH-135A).
It was launched in 2018 by Chief Minister Yogi Adityanath and land acquisition was started in February 2019 by the Government of Uttar Pradesh.[3] The total project value of Gorakhpur Link Expressway, including the land acquisition cost is around ₹ 5,876 crores.[2][4]
Route
[edit]The Gorakhpur Link Expressway will connect Jaitpur village on Gorakhpur Bypass in Gorakhpur district with Salarpur village (south of Jalalpur) on Purvanchal Expressway in Azamgarh district.[2] It will pass through 4 districts of Uttar Pradesh i.e. Gorakhpur, Sant Kabir Nagar, Ambedkar Nagar and Azamgarh.
Construction
[edit]The construction cost (excluding the cost of Land) is around ₹3,024 crores. Around 1,095 hectares (2,710 acres) of land will be acquired for this project.[5][6] 2 Toll Plaza, 3 ramp plaza, 7 Flyovers, 7 major bridges, 27 minor bridges, 16 vehicular-underpasses (VUP), 50 Light VUP and 35 pedestrian underpasses will also be constructed.
The construction work of the 91.352 km long Gorakhpur Link Expressway is divided into 2 packages:
Sr. No | Package | Length in km | Contractor |
---|---|---|---|
1. | Jaitpur (Gorakhpur)–Fulwariya (Ambedkar Nagar) | 48.317 | Apco Infratech |
2. | Fulwariya (Ambedkar Nagar)–Salarpur (Azamgarh) | 43.035 | Dilip Buildcon Limited[7] |
Status updates
[edit]- Feb 2019: Land acquisition work started by Government of Uttar Pradesh.[3]
- Oct 2019: 50% of the required land has been acquired. Construction work is divided in 2 packages.[8]
- Nov 2019: Dilip Buildcon Ltd receives Letter of Acceptance (LoA) for Package-2 on 29 November 2019.
- Feb 2020: Construction work started on 10 February for Package-1 by Apco Infratech.
- Apr 2020: Road construction work resumed.[9]
- Jun 2020: Construction work started on 19 June for Package-2 by Dilip Buildcon.[10]
- Mar 2021: 1,044 out of 1,095 Hectares (95.36%) of required land has been acquired till 30 March.
- Jun 2021: 24% of construction work and 50% of earthwork is completed as of 28 June.[11]
- Aug 2021: 27.4% of construction work completed as of 16 August, 2021.[12]
- Nov 2021: 29% of construction work completed as of 8 November, 2021.[13]
- Jan 2022: 50% of the earthwork and 34% of construction work has been completed.[14]
- April 2022: As of 25 April, 39.57% of overall construction work including 65% of earthwork and 265 out of 339 structures have been completed.
- May 2022: 69% of earthwork and 45% of overall construction work has been completed. 282 structures out of 339 have been completed.
- July 2022: 71% of earthwork and 49% of overall construction work has been completed. 286 structures out of 342 have been completed.
- August 2022: 75% of earthwork and 52% of overall construction work has been completed. 289 structures out of 342 have been completed.
- March 2023: 62% of overall construction work has been completed, 319 structures out of 342 have been completed. and is now confirmed to become operational by December 2023.[15]
- September 2023: 96% of earthwork and 81% of overall Construction work has been completed, 336 structures out of 341 have been completed.
- May 2024: 100% of earthwork and 95% of overall Construction work has been completed, 337 structures out of 341 have been completed.[16]
See also
[edit]- Purvanchal Expressway
- Agra-Lucknow Expressway
- Bundelkhand Expressway
- Awadh Expressway
- Ganga Expressway
- Udyog Path
- Kisan Path
External links
[edit]References
[edit]- ^ "Soon, Gorakhpur Link Expressway to be operational in UP". The Times of India. 21 March 2023. Retrieved 22 March 2023.
- ^ a b c "About Gorakhpur Link Expressway project". UPEIDA. Retrieved 12 July 2021.
- ^ a b "About Gorakhpur Link Expressway". The Metro Rail Guy. Retrieved 10 July 2021.
- ^ "Gorakhpur Link Expressway: faster connectivity from Lucknow, Agra and Delhi with 91 km long expressway". Financial Express. 22 June 2020.
- ^ "Consortium of banks sanctions Rs 250 crore for Gorakhpur Link e-way". The Pioneer.
- ^ "UP approves Rs 454 crore more for 2 highways totaling Rs 20,000 crore". Business Standard.
- ^ "Dilip Buildcon Ltd receives LoA for Gorakhpur Link Expressway project". Business Standard. 30 November 2019.
- ^ "UP picks 4 developers for two expressway projects worth Rs 20,000 crore". Business Standard.
- ^ "UP: Work resumes on key Expressways". Times of India.
- ^ "274 crore released for Gorakhpur link expressway by UPEIDA". Amar Ujala.
- ^ "Progress report of Gorakhpur Link Expressway (June 2021)" (PDF). UPEIDA. Archived from the original (PDF) on 28 June 2021. Retrieved 28 June 2021.
- ^ "Progress report of Gorakhpur Link Expressway (August 2021)" (PDF). UPEIDA. Retrieved 16 August 2021.
- ^ "Progress report of Gorakhpur Link Expressway (8 November 2021)" (PDF). UPEIDA. Retrieved 8 November 2021.
- ^ "Progress report of Gorakhpur Link Expressway (23 November 2021)" (PDF). upeida. Retrieved 23 November 2021.
- ^ "Soon, Gorakhpur Link Expressway to be operational in UP". The Times of India. 21 March 2023. Retrieved 22 March 2023.
- ^ "Gorakhpur Link Expressway Progress Report" (PDF). upeida. 6 May 2024. Retrieved 8 May 2024.