[edit]The links in this section for the three common misconceptions are now outdated.
Guidance Notes and Further Information[edit]
Guidance Notes and Flow Charts are published by the ICE. These notes are supplemented by the Frequently Asked Questions sections of the NEC website.[6] Prospective users of the NEC3 contract are encouraged to study the FAQ's in order to avoid unintended contract provisions. The often unintended Option C scenario where a Contractor is paid monies in excess of the Target Cost plus maximum share provisions is specifically not addressed in the guidance notes / Frequently Asked Questions. Other common misinterpretations are minutes of meetings as communications, deleted work and paying for correcting defects. Employers often utilise the additional conditions of contract (Z-clauses) to amend or delete contract provisions relating to these items.